Title
Recommendation to Authorize the City Manager to Execute a Third Amendment to the Project Funding Agreement with the Alameda County Transportation Commission to Extend the Expiration Date of the Clement Avenue / Tilden Way Project to December 31, 2028.
In accordance with California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Section 15301 (Existing Facilities) and Section 15304 (Minor Alterations to Land). (Public Works 31041520)
Body
To: Honorable Mayor and Members of the City Council
From: Gerry Beaudin, City Manager
EXECUTIVE SUMMARY
The Clement Avenue/Tilden Way Project (the Project) broke ground in December 2025 and is currently under construction. The Project is funded with Measure BB Funds under a Project Funding Agreement (Agreement) with Alameda County Transportation Commission (ACTC). The current Agreement expires on December 31, 2026. Staff recommends the City Council authorize the City Manager to execute a Third Amendment to the Agreement with ACTC to extend the expiration date to December 31, 2028. The proposed Third Amendment is included as Exhibit 2.
BACKGROUND
In 2018, the City executed an Agreement with ACTC for $2,019,000 of Measure BB Funds for Clement Avenue/Tilden Way Project, with an expiration date of December 31, 2020.
In 2021, the City executed the First Amendment and Restated Agreement with ACTC to extend the expiration date to December 31, 2022.
In 2023, the City executed the Second Amendment to Agreement with ACTC to accept an additional $6,376,000, totaling $8,395,000 of Measure BB Funds dedicated to the Clement Avenue and Tilden Way Project and to extend the expiration date to December 31, 2026.
DISCUSSION
The current Agreement expires on December 31, 2026, limiting the City’s ability to claim reimbursement funds to those incurred after that date. Staff expects to continue requesting reimbursement for Measure BB costs beyond December 31, 2026.
The Project is currently under construction and scheduled for substantial completion in early 2027; however, the post-construction closeout process takes several months and includes project punch list, obtaining as-builts, and formal City Council acceptance of the improvements.
Under the terms of the Agreement, the City is required to provide regular reports to ACTC on project progress, Measure BB funds expended for the project, and a final report on all project activities.
Staff recommends City Council authorize the City Manager to execute a Third Amendment to the Project Funding Agreement with ACTC to extend the expiration date of the Agreement to December 31, 2028. Although the project is expected to be complete well before this date, having additional time prevents the need for another amendment. The additional time will allow the City to administratively closeout the Project with ACTC.
ALTERNATIVES
City Council may consider the following alternatives to the staff recommendation, as well as other alternatives not identified below:
• Direct changes to the Third Amendment of the Agreement with ACTC. This is not recommended because changes to the proposed amendment could affect the City's ability to fully utilize the Measure BB funds allocated to the Project
• Do not authorize the Third Amendment. This is not recommended because the Agreement would expire on December 31, 2026, potentially affecting the City's ability to obtain reimbursement for eligible Project costs incurred or processed after that date.
FINANCIAL IMPACT
The total budget for the Clement Avenue/Tilden Way Project (C65300) is $14.1 million, including $8,395,000 in Measure BB Funds. To date, the City has received $4,606,543 of Measure BB funds. The remaining $3,788,457 in Measure BB funds remains eligible for reimbursement. Extending the Agreement expiration date will provide additional time for the City to complete construction, perform project closeout, and submit any remaining eligible reimbursement requests in accordance with the Agreement. The amendment will not increase the Measure BB funding allocation and will have no impact on the General Fund.
MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE
The recommended improvements to the Project are consistent with the Alameda General Plan mobility goals, including Equity, Safety Choices, and Sustainability.
The improvements are included in the City of Alameda 2023 Strategic Plan as Project # TIE14b (investment in transportation, infrastructure, economic opportunities, and historic resources), and are consistent with the Active Transportation Plan, which includes a separated bikeway along Clement Avenue and Tilden Way, and the 2023 Infrastructure Plan that includes Project #3: Clement Avenue: Cross Alameda Trail Gap Closures.
This action is subject to the Levine Act.
ENVIRONMENTAL REVIEW
In accordance with CEQA, this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Section 15301 (Existing Facilities) and Section 15304 (Minor Alterations to Land).
CLIMATE IMPACT
Since vehicle miles traveled are the largest source of greenhouse gas emissions in Alameda, safety improvements for pedestrians, bicyclists, and transit users will have a positive climate impact.
RECOMMENDATION
Authorize the City Manager to execute a Third Amendment to a Project Funding Agreement with the Alameda County Transportation Commission to extend the expiration date of the Clement Avenue / Tilden Way Project to December 31, 2028.
Respectfully submitted,
Erin Smith, Public Works Director
By,
Scott Wikstrom, City Engineer
Brendin Christolear, Supervising Civil Engineer
Ali Hatefi, Senior Engineer
Financial Impact section reviewed,
John Stefanski, Interim Assistant City Manager/Acting Finance Director
Exhibits:
1. Alameda CTC Project Funding Agreement, First and Second Amendments
2. Third Amendment