File #: 2024-4161   
Type: Consent Calendar Item
Body: City Council
On agenda: 7/16/2024
Title: Recommendation to Accept the Work of JMB Construction for the Storm Drain Pump Station Electric Upgrades Project, No. P.W. 9-19-48. In accordance with the California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities). (Public Works 310)

Title

 

Recommendation to Accept the Work of JMB Construction for the Storm Drain Pump Station Electric Upgrades Project, No. P.W. 9-19-48.

In accordance with the California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities).  (Public Works 310)

Body

 

To: Honorable Mayor and Members of the City Council

 

From: Jennifer Ott, City Manager

 

EXECUTIVE SUMMARY

 

On October 19, 2021, City Council awarded a contract to JMB Construction for the Storm Drain Pump Station Electrical Upgrades Project. The project consists of upgrades to the electrical and control equipment at four pump stations, and installation of a new wet well and pumps at one of the stations.  The improvements and maintenance executed under the subject contract are complete in accordance with project plans and specifications. Staff recommends City Council acceptance of the work.

 

BACKGROUND

 

The City of Alameda’s (City) stormwater drainage system consists of an extensive curb/gutter system, 1,655 intersection and sidewalk culverts, 126 miles of buried pipelines, 11 pump stations, several lagoons with tide gates and 278 outfalls. The system is designed to take stormwater runoff from roads, roofs, and impervious surfaces, until it is ultimately discharged to the Bay through outfalls.  Ensuring the long-term viability of the City’s storm system is critical for ensuring proper drainage to prevent roads and neighborhoods from flooding during storm events.

 

In accordance with the 2011 Storm Drain Master Plan and Storm Drain Pump Station Assessment, staff developed a project to replace the existing electrical equipment at four storm drain pump stations:  Main Street, Webster Street, Third Street, and Golf Course Stations.  Equipment replaced and installed included control panels, service pedestals, SCADA poles, concrete pads, stairs, fences, gates, electrical equipment, and other items.  The Third Street station received a new wet well and pumps.

 

DISCUSSION

 

On October 19, 2021, City Council awarded a contract in the amount of $2,030,900, including contingencies, to JMB Construction. Although the project schedule was impacted due to supply chain constraints and wet weather during construction, the project was completed in accordance with the plans and specifications and acceptable to the Public Works Department.  The final cost, including all extra work orders, is $1,916,957.76.

 

 

ALTERNATIVES

 

                     Accept contract as presented.

                     Do not accept the contract and provide different direction to staff.

 

FINANCIAL IMPACT

 

The project was budgeted in the Public Works Department’s CIP Program (91606), with funds in the amount of $2,130,900.00.  The funding source for this project was the Stormwater Fund (Fund 264). There is no impact to the General Fund.

 

MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE

 

This action is consistent with the Alameda Municipal Code.

 

Strategic Plan Project CC8: Design and implement upgrades for stormwater infrastructure to reduce local flooding, including the cleaning of storm drains and increasing pump station capacity.

 

ENVIRONMENTAL REVIEW

 

In accordance with CEQA, this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities).

 

CLIMATE IMPACTS

 

The project increases the resiliency of the stormwater drainage system by improving the operations of existing pump stations and accommodating expected increases in storm intensity due to climate change. All electrical panels were constructed above the existing base flood elevation plus three (3) feet of sea level rise.

 

RECOMMENDATION

 

Accept the Work of JMB construction for the Storm Drain Pump Station Electric Upgrades Project, No. P.W. 9-19-48.

 

Respectfully submitted,

Erin Smith, Public Works Director

 

By,

Flavio D. Barrantes, Project Manager III

 

Financial Impact section reviewed,

Margaret L. O'Brien, Finance Director