Legislation Details

File #: 2026-6472   
Type: Regular Agenda Item
Body: City Council
On agenda: 12/1/2026
Title: Recommendation to Receive a Status Update on the Clement Avenue Truck Route between Grand Street and Sherman Street and Direct Staff to Maintain the Existing Truck Route or Evaluate Other Truck Route Options for Further Consideration; and Adoption of Resolution Amending Fiscal Year 2026-27 Budget Appropriation from the General Fund Unassigned Fund Balance for Costs Associated with a General Plan Amendment to Amend the City’s Designated Truck Route. (Public Works 31041520)
Attachments: 1. Exhibit 1: 1990 General Plan Truck Routes, 2. Exhibit 2: General Plan Street Classification Appendix 2023, 3. Exhibit 3: Clement Avenue Swept Path and Lane Widths, 4. Exhibit 4: Conceptual Modifications at Clement and Stanton, 5. Exhibit 5: Clement Avenue Parking Utilization Study, 6. Exhibit 6: Truck Route Options, 7. Resolution

Title

Recommendation to Receive a Status Update on the Clement Avenue Truck Route between Grand Street and Sherman Street and Direct Staff to Maintain the Existing Truck Route or Evaluate Other Truck Route Options for Further Consideration; and
Adoption of Resolution Amending Fiscal Year 2026-27 Budget Appropriation from the General Fund Unassigned Fund Balance for Costs Associated with a General Plan Amendment to Amend the City’s Designated Truck Route. (Public Works 31041520)
Body
To: Honorable Mayor and Members of the City Council

From: Gerry Beaudin, City Manager

EXECUTIVE SUMMARY

The Skyline development project at 2015 Grand Street (former Pennzoil facility) has completed the final gap in Clement Avenue extension, and the roadway from Hibbard Street to Grand Street is ready to open to traffic. Relocation of the truck route from Buena Vista Avenue to Clement Avenue between Sherman Street and Grand Street has long been a component of the City of Alameda’s (City) General Plan. City Council requested a status update and expressed interest in considering other truck route options. This report presents five potential options, including maintaining the truck route on Clement Avenue, to City Council for consideration. Additional analysis, public outreach, and a General Plan Amendment (GPA) would be required if City Council directs Staff to consider truck route option(s) other than on Clement Avenue between Grand Street and Sherman Street. Evaluation and consideration of a GPA is anticipated to take 9-12 months. Additionally, staff recommends an interim action to open Clement Avenue to vehicular traffic at Grand Street prior to completion of the GPA.

BACKGROUND

History
The truck route map from the 1990 General Plan (Exhibit 1) included east-west truck routes through the central portion of Alameda Island on seven roadways: Shore Line Drive, Otis Drive, Encinal Avenue, Central Avenue, Lincoln Avenue, Buena Vista Avenue, and Clement Avenue. In 2009, City C...

Click here for full text