Title
Recommendation to Accept the Work of Mountain Cascade Inc. for Construction of Group 4 Sewer Pump Station Renovations for Reliability and Safety Improvements Project, No. P.W. 08-17-37.
In accordance with the California Environmental Quality Act (CEQA), the project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Sections 15301 (Existing Facilities). (Public Works 31040520)
Body
To: Honorable Mayor and Members of the City Council
From: Jennifer Ott, City Manager
EXECUTIVE SUMMARY
On March 3, 2020, City Council awarded an agreement to Mountain Cascade Inc. for construction of the Group 4 Sewer Pump Station Renovations for Reliability and Safety Improvements Project, No. P.W. 08-17-37 (Public Works C22000). The scope of work included rehabilitation of existing structural facilities, construction of new wet wells and manholes, replacement of force and gravity mains, replacement of pumps, piping, valves, electrical equipment, control panels and the installation of stand-by generators.
The agreement improvements are complete in accordance with project plans and specifications at a total cost of $5,025,627.93. Staff recommends City Council accept the work.
BACKGROUND
The City of Alameda's (City) sanitary sewer system has over 40 pump stations. The Group 4 pump station project prioritized improvements at seven pump stations based on condition assessment, consequence of sewer system overflows (SSOs), and reliability and safety. The scope of work included rehabilitation of existing structural facilities, construction of new wet wells and manholes, replacement of force and gravity mains, replacement of pumps, piping, valves, electrical equipment, control panels and the installation of stand-by generators.
DISCUSSION
On March 3, 2020, City Council awarded an agreement to Mountain Cascade Inc. in the amount of $5,749,133, including contingencies. Sanitary sewer pump station rehabil...