File #: 2023-3586   
Type: Consent Calendar Item
Body: City Council
On agenda: 12/5/2023
Title: Recommendation to Accept the Work of McGuire & Hester, for the 2022-23 Pavement Management Project, Phase 41, No. P.W. 05-22-16. In accordance with the California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Section 15301 (Existing Facilities). (Public Works 31041520)
Title
Recommendation to Accept the Work of McGuire & Hester, for the 2022-23 Pavement Management Project, Phase 41, No. P.W. 05-22-16.
In accordance with the California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Section 15301 (Existing Facilities). (Public Works 31041520)

Body

To: Honorable Mayor and Members of the City Council

From: Jennifer Ott, City Manager

EXECUTIVE SUMMARY

The City of Alameda (City) maintains over 144 centerline miles of roadway providing access and circulation to every resident and business in the City. The City's Pavement Management Program, in combination with the City's Maintenance Service Center, works to maintain this network through a combination of maintenance and rehabilitation activities including an annual capital project. The 2022-23 pavement management program, phase 41, included pavement overlays, slurry sealing and crack sealing for approximately 5.5 miles of roadway. The improvements executed under the subject contract are complete and acceptable to staff. Staff recommends that City Council accept the work.

BACKGROUND

The City's pavement management program, in combination with the City's Maintenance Service Center, works to maintain the street network through a combination of maintenance and rehabilitation activities including an annual capital project.

Each year, the capital project focuses on one of the three planning zones throughout the City, rotating from the west zone (west of Grand Street), to the central zone (between Grand Street and High Street), and to the Bay Farm Island zone (east high of High Street), and then back to the west zone.

The 2022-23 pavement management program, phase 41, project is located in the west zone and includes both preventive maintenance treatments (namely slurry sealing and crack sealing) and roadway rehabilitation treatments (overlays and full depth reclamation).

Preventive maintenance ...