In accordance with the California Environmental Quality Act (CEQA), this action is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities), 15302 (Replacement or Reconstruction), and 15303 (New Construction of Small Structures). (Public Works 60341591)
Body
To: Honorable Mayor and Members of the City Council
From: Jennifer Ott, City Manager
EXECUTIVE SUMMARY
On November 15, 2022, City Council awarded the Police Department Reception Area and Ramp Renovation Project to G&G Builders. The project increased accessibility and provided enhanced safety measures for staff. The construction scope executed under the subject agreement is complete and acceptable to Public Works. Staff recommends City Council authorize the City Manager to accept the work.
BACKGROUND
The City's Police Department building, located at 1555 Oak Street, is a 35,184 square foot, two-story structure with a full basement. The facility, built in 1977, was designed and constructed to specifically house the Alameda Police Department. Funding for the Reception Area and Ramp Renovation Project (Project) was appropriated in the 2017-2019 Capital Improvement Program. The now completed Project has enhanced accessibility by widening the existing ramp entrance, adding ADA-compliant handrails, replacing the lobby and elevator door controls with modernized push-button controls, and modifications to the reception and service counter/window. Additionally, the non-compliant fire-rated walls, windows, and door assemblies were upgraded to comply with current codes, the floor and soffit/ceiling finishes restored, and the reception area fa?ade renovated for improved security.
DISCUSSION
On Tuesday, November 15, 2022, City Council awarded a contract in the ...