File #: 2016-3033   
Type: Regular Agenda Item
Body: Planning Board
On agenda: 6/22/2016
Title: PLN16-0165 - Westmont of Harbor Bay Assisted Living. Applicant: Chris Garwood for Pacific Union Land Investors LLC. Public hearing to consider a revision to the previously approved Final Development Plan PLN15-0092 (Esplanade site) to allow construction of an approximately 105,500-square-foot, two-story senior assisted living facility on the remainder of the undeveloped portion of the property at 2900 Harbor Bay Parkway. The site is located within a CM-PD Commercial Manufacturing Planned Development Zoning District in the Harbor Bay Business Park. Pursuant to CEQA Guidelines Section 15162, there have been no significant changes in circumstances that require revisions to the previously certified Environmental Impact Report. The proposed project is not likely to cause substantial environmental damage or substantially and avoidably injure endangered, rare, or threatened fish or wildlife or their habitat.
Attachments: 1. Exhibit 1 - Prior Project Plans, 2. Exhibit 2a - Project Plans, 3. Exhibit 2b - Project Plans, 4. Exhibit 3 - Environmental Review, 5. Exhibit 4 - Correspondence, 6. Exhibit 5 - Draft Resolution, 7. Additional Correspondence (rec'd up to 3 pm 6-22-16)
Title

PLN16-0165 - Westmont of Harbor Bay Assisted Living. Applicant: Chris Garwood for Pacific Union Land Investors LLC. Public hearing to consider a revision to the previously approved Final Development Plan PLN15-0092 (Esplanade site) to allow construction of an approximately 105,500-square-foot, two-story senior assisted living facility on the remainder of the undeveloped portion of the property at 2900 Harbor Bay Parkway. The site is located within a CM-PD Commercial Manufacturing Planned Development Zoning District in the Harbor Bay Business Park.

Pursuant to CEQA Guidelines Section 15162, there have been no significant changes in circumstances that require revisions to the previously certified Environmental Impact Report. The proposed project is not likely to cause substantial environmental damage or substantially and avoidably injure endangered, rare, or threatened fish or wildlife or their habitat.


Body

To: Honorable President and
Members of the Planning Board

From: Henry Dong
Planner I

BACKGROUND

The project is located on a vacant 5.5 acre portion of an existing 9.22 acre property located approximately 600 feet west of the corner of Harbor Bay Parkway and Adelphian Way known as the "Esplanade Project". The first phases of the Esplanade Project include the Stacey & Witbeck and the McGuire and Hester office buildings to the east of the site. The Harbor Bay ferry terminal parking lot is immediately to the west of the site, and a lagoon and residential neighborhood border the site to the north. The property fronts onto the San Francisco Bay to the south.

On February 25, 2008, the Planning Board approved the original Esplanade Plan (PLN07-0061) to allow construction of ten office buildings totaling 109,000 square feet on the 9.22 acre Esplanade site. The Esplanade Project is located in the Harbor Bay Business Park and is zoned Commercial Manufacturing (CM) with a Planned Development (PD) ...

Click here for full text