File #: 2016-3603   
Type: Consent Calendar Item
Body: City Council
On agenda: 12/6/2016
Title: Recommendation to Award a Contract in the Amount of $252,230, Including Contingencies, to Andy's Roofing Company, Inc. for the Maintenance Service Center Roof Replacement, No. P.W. 19-16-18. (Public Works 706)
Attachments: 1. Exhibit 1 - Contract

Title

 

Recommendation to Award a Contract in the Amount of $252,230, Including Contingencies, to Andy’s Roofing Company, Inc. for the Maintenance Service Center Roof Replacement, No. P.W. 19-16-18. (Public Works 706)

Body

To: Honorable Mayor and Members of the City Council

 

From: Jill Keimach, City Manager

 

Re: Recommendation to Award a Contract in the Amount of $252,230, Including Contingencies, to Andy’s Roofing Company, Inc. for the Maintenance Service Center Roof Replacement, No. P.W. 19-16-18

 

BACKGROUND

 

The Maintenance Service Center, located at 1616 Fortmann Way, requires a roof replacement. The work includes, but is not limited to, complete installation of a roofing system that is watertight, resists uplift pressures, and performs normally through exposure to the next fifteen years of weather.

 

DISCUSSION

 

To solicit the maximum number of bids and the most competitive price, a notice inviting bids and project specifications was advertised in 12 separate builders exchanges throughout the Bay Area. The notice inviting bids was also published in the Alameda Journal and put on the City’s website. Eight contractors submitted bids. Bids were publicly opened and read aloud on Monday, October 10, 2016. The list of bidders from lowest to highest for the total project cost is as follows:

 

Bidder

Location

Bid Amount

Andy’s Roofing Company, Inc.

San Leandro

$229,300

Roofing and Solar Contracting

Hayward

$237,500

Pioneer Contractors, Inc.

San Francisco

$276,000

Best Contracting Services, Inc.

Gardena

$279,500

Joseph Murphy Construction, Inc.

Livermore

$286,244

Central Bay Roofing & Restoration

Alameda

$332,157

Stronger Building Services

San Leandro

$350,000

Southwest Construction

San Bruno

$399,460

 

Public Works staff contacted several references provided by Andy’s Roofing Company, Inc., the lowest responsible and responsive bidder, and received positive feedback on the ability of the company to meet the project requirements and the quality and timeliness of their work. Staff checked the California Contractors State License Board and verified that the contractor’s license is current and active.

 

Staff recommends awarding a contract to Andy’s Roofing Company, Inc. for a total amount of $252,230, which includes a ten percent contingency in the amount of $22,930.  The contractor is not guaranteed any of the contingency amount, and use of the contingency will be at the sole discretion of the City Engineer for work not originally anticipated in the plans and specifications. The project specifications inform the successful bidder that they shall pay not less than the prevailing rate of per diem wages as determined by the Director of the California Department of Industrial Relations.  A copy of the contract is attached as Exhibit 1.

 

FINANCIAL IMPACT

 

The project is budgeted in the Capital Improvement Program (Project No. 91609706) for the Maintenance Service Center roof replacement project with monies allocated from Facility Maintenance (Fund 706). The City Council allocated $420,000 for this project on September 15, 2015. There is no impact to the General Fund.

 

MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE

 

This action does not affect the Municipal Code.

 

ENVIRONMENTAL REVIEW

 

In accordance with the California Environmental Quality Act (CEQA), this project is Categorically Exempt under CEQA Guidelines Section 15301(b), Existing Facilities.

 

RECOMMENDATION

 

Award a contract in the amount of $252,230, including contingencies, to Andy’s Roofing Company, Inc. for the Maintenance Service Center roof replacement, No. P.W. 19-16-18.

 

Respectfully submitted,

Bob Haun, Public Works Director

 

By,

Abdulla Ahmed, Project Manager II

 

Financial Impact section reviewed,

Elena Adair, Finance Director

 

Exhibit:

1.                     Andy’s Roofing Company Contract