Title: Del Monte Development Project Annual Report. The Planning Board will consider an annual report documenting compliance with the 2014 Del Monte Warehouse Development Agreement. The consideration of an Annual Report is not a project under the California Environmental Quality Act (CEQA). No further environmental review is required.
Attachments: 1. Exhibit 1 TL Partners I, LP Letter dated April 27, 2017, 2. Exhibit 2 Draft Planning Board Resolution for Del Monte
Title

Del Monte Development Project Annual Report. The Planning Board will consider an annual report documenting compliance with the 2014 Del Monte Warehouse Development Agreement. The consideration of an Annual Report is not a project under the California Environmental Quality Act (CEQA). No further environmental review is required.

Body

To: Honorable President and
Members of the Planning Board

From: Andrew Thomas
Assistant Community Development Director

Date: March 27, 2017

Re: Annual Review: Del Monte Development Agreement - Applicant: TL Partners I, LP. The applicant requests a periodic review of a Development Agreement related to the Del Monte Warehouse Master Plan. The consideration of an Annual Report is not a project under the California Environmental Quality Act (CEQA). No further environmental review is required.

BACKGROUND

In January 2015, the City of Alameda and TL Partners I, LP ("Developer"), entered into a Development Agreement (DA) for the "Del Monte Warehouse Master Plan."

Alameda Municipal Code ("AMC") Section 30-95.1 authorizes the Planning Board to conduct a public hearing at which the applicant must demonstrate good faith compliance with the terms and conditions of the DA. In order to demonstrate good faith compliance, the applicant has submitted a Developer Letter of Compliance (Exhibit 1) for the annual review as required under AMC Section 30-95.1 and Article 5 of the DA.

This annual review reports on activities and developments taking place from January 1, 2016, through December 31, 2016.

ANALYSIS

During the Development Agreement Annual Review Period (January 1, 2016 through December 31, 2016), TL Partners I, LP and the City worked together on several activities. Those activities are summarized below and described in full in Exhibit 1:

* Jean Sweeney Open Space Park: The Developer is obligated to make a payment of $2,000,000 in order to fund portio...