Title
Status Report on the Alameda Point Gym Restroom Project (10 minutes)
Body
To: Honorable Chair and Members of the Recreation and Park Commission
From: Amy Wooldridge, Recreation and Parks Director
Re: Status Report on the Alameda Point Gym Restroom Project
BACKGROUND
The City Council authorized $175,000 for construction of a modular restroom building that would serve the Alameda Point Gymnasium and additional funds were identified and allocated from the Mastick Senior Center front entrance project which was determined to be not needed. A total of $280,000 is available for this project. This project is managed by Public Works as part of the Capital Improvement Program for Building Maintenance.
DISCUSSION
Public Works solicited proposals from several firms for design of the restroom. The most responsive and lowest cost proposal was with Byrens Kim, a firm that is experienced in modular building design. This design work includes the civil engineering to bring utilities from West Redline Ave. as well as the specifications of the modular building. This restroom is planned to be on the northwest side of the gym on the parking lot side, accessible from an existing exit, and will serve as restroom facilities for both gymnasium and skate park users.
Below is the tentative design, bid and award schedule for the Alameda Gym Modular Restroom:
Tentative Schedule
Task
Estimated Date of Completion
Execute contract with Byrens Kim for Design Services in the amount of $69,100
May 2018
Start Design
June 2018
Recreation and Park Commission Design Review
September 2018
Complete design and permits including plans, specifications and estimate (PS&E)
November 2018
Bid Advertise
December 2018
City Council Award Contract and appropriate additional funds if necessary
February 2019
Execute contract ...