Title: Annual Review: Alameda Point Site A Development Agreement - Applicant: Alameda Point Partners, LLC (APP). Approve a Resolution Finding that APP has Demonstrated Good Faith Compliance with the Terms and Conditions of the Alameda Point Site A Development Agreement from April 15, 2018 through April 15, 2019, based on the Findings contained in the Draft Resolution. This Compliance Review is not a project under CEQA
Attachments: 1. Exhibit 1 APP Letter dated March 20, 2018, 2. Exhibit 2 Draft Planning Board Resolution
Title

Annual Review: Alameda Point Site A Development Agreement - Applicant: Alameda Point Partners, LLC (APP). Approve a Resolution Finding that APP has Demonstrated Good Faith Compliance with the Terms and Conditions of the Alameda Point Site A Development Agreement from April 15, 2018 through April 15, 2019, based on the Findings contained in the Draft Resolution. This Compliance Review is not a project under CEQA

Body

To: Honorable President and
Members of the Planning Board

From: Andrew Thomas
Acting Planning Building and Transportation Director

Date: April 8, 2019

BACKGROUND

On August 31, 2015, the City of Alameda and Alameda Point Partners (APP) ("Developer") entered into a Development Agreement for the 68-acre Site A project at Alameda Point.

Pursuant to State law, Alameda Municipal Code (AMC) Section 30-95.1, and Article 5 of the Development Agreement, the Planning Board is required to hold a public hearing at which the applicant must demonstrate good faith compliance with the terms and conditions of the Agreement. In order to demonstrate good faith compliance, the applicant has submitted a Developer Letter of Compliance (Exhibit 1) for the annual review from April 15, 2018 through April 15, 2019.

ANALYSIS

During the review period, the Developer has been working with the City of Alameda and its design and construction teams to complete the construction drawings and begin work on the first phases of the Site A development. During the review period, the Developer met regularly with City staff to ensure compliance with the Development Agreement and successful implementation of the project.

Exhibit 1 outlines actions taken by the Developer and the City during the period under review. The following sections of this report briefly summarize the major actions taken during the review period to implement the project and the provisions of the Development Agreement.

Infrastructure: Since approval of the Site A Development ...

Click here for full text