File #: 2019-7349   
Type: Regular Agenda Item
Body: Planning Board
On agenda: 10/14/2019
Title: PLN19-0270 - Development Plan and Design Review - 1815 Clement Avenue (between Alameda Marina Drive and Schiller Street) - Applicant: Pacific Shops, LLC. Public Hearing to consider Development Plan and Design Review application for a four- to five-story residential building with 360 multi-family units and 8 Work/Live units as part of Phase I of the Alameda Marina Master Plan project. The environmental effects of the proposed project were considered and disclosed in the Alameda Marina Master Plan Environmental Impact Report (State Clearinghouse #2016102064). No further environmental review is required under the California Environmental Quality Act.
Attachments: 1. Exhibit 1 - Alameda Marina Phase I Development Plan and Design Review Plan, 2. Exhibit 2 - Draft Resolution
Title

PLN19-0270 - Development Plan and Design Review - 1815 Clement Avenue (between Alameda Marina Drive and Schiller Street) - Applicant: Pacific Shops, LLC. Public Hearing to consider Development Plan and Design Review application for a four- to five-story residential building with 360 multi-family units and 8 Work/Live units as part of Phase I of the Alameda Marina Master Plan project. The environmental effects of the proposed project were considered and disclosed in the Alameda Marina Master Plan Environmental Impact Report (State Clearinghouse #2016102064). No further environmental review is required under the California Environmental Quality Act.

Body

To: Honorable President and Members of the Planning Board

From: Allen Tai, City Planner


BACKGROUND
In July 2018, the City Council approved the Alameda Marina Master Plan, which established requirements for the development of a mixed use plan for the Alameda Marina site that includes up to 760 multifamily housing units, up to 250,000 square feet of commercial and maritime commercial space, approximately 3.59 acres of shoreline open space, and a 530 slip marina.

On June 24, 2019, the Planning Board held a Study Session on the first phase of the Master Plan project "Wrap A," which consists of construction of the first multi-family residential building that now includes 360 units and 8 Work/Live units. The Planning Board provided comments on the project design, which the applicant addressed in revised plans. The applicant is now requesting Planning Board approval of the Development Plan and Design Review application for Wrap A.

DISCUSSION
Project Summary:

The Alameda Marina Master Plan requires Development Plan and Design Review approval for buildings in each phase of the master plan project. This proposal consists of the first phase ("Wrap A") located on the western edge of the project site along Clement Avenue between Alameda Marina Drive and Schiller Street. This 3.9-acre area of the Alameda...