File #: 2020-8531   
Type: Consent Calendar Item
Body: City Council
On agenda: 12/15/2020
Title: Recommendation to Accept the Work of Innovative Construction Solutions for the Alameda South Shore Lagoons 3 and 5 Dredging Project, No. P.W. 09-19-49. (Public Works 96007)

Title

 

Recommendation to Accept the Work of Innovative Construction Solutions for the Alameda South Shore Lagoons 3 and 5 Dredging Project, No. P.W. 09-19-49. (Public Works 96007)

 

Body

 

To: Honorable Mayor and Members of the City Council

 

EXECUTIVE SUMMARY

 

On April 7, 2020, the City Council awarded a contract to Innovative Construction Solutions in the amount of $407,184, which included a 20% contingency, for the removal of accumulated sediment from the corners of Lagoons 3 and 5 of the South Shore lagoon system. Unforeseen extra work required an additional purchase order of $2,447 to complete the project.  Sufficient funding was available in the Capital Improvement Program (CIP) Fund 96007 to pay for the additional expense with a total project cost of $409,631.  The project has been completed and is acceptable to the Public Works Department.

 

BACKGROUND

 

The project included mechanically dredging the lagoon corners to remove accumulated sediment. The dredge spoils were loaded into trucks and hauled to suitable disposal sites that accepted the material. The dredging took place in August and September 2020 during the annual lowering of the lagoons for maintenance to minimize disturbance of the lagoons and lagoon water quality.

 

DISCUSSION

 

On April 7, 2020, the City Council awarded a contract to Innovative Construction Solutions in the amount of $407,184.  Poor sediment consistency of the dredged material demanded use of additional soil desiccant to transport the material to the designated disposal facility.  A purchase order for the additional soil desiccant cost ($2,447) was issued from CIP Fund 96007.

 

The project has been completed and is acceptable to the Public Works Department.  The final project cost, including the additional soil desiccant tonnage of $2,447, is $409,631.

 

ALTERNATIVES

 

                     Accept project as presented; or

                     Do not accept project and provide different direction to staff.

 

FINANCIAL IMPACT

 

The original funds were budgeted in the Public Works Department account for CIP Fund 96007, Lagoon Maintenance.  The allocation for the lagoon dredging project was $407,184.  An additional purchase order from CIP Fund 96007 of $2,447 was needed to complete the project. 

 

LAGOONS 3 AND 5 DREDGING PROJECT FUNDING

Funding Source

Approval

Budget

General Fund

FY2019-21

$400,000

Alameda West Lagoon HOA

FY2019-21

$267,128

Urban Runoff (351)

FY2017-19

$250,000

TOTAL

 

$917,128

 

A summary of project expenditures is below.

 

LAGOONS 3 AND 5 DREDGING PROJECT EXPENDITURES

Project Tasks

Authorized

Expended to Date

Planning and Design (allowance)

$110,000

$110,000

Original Contract

$407,184

$409,631

Admin/Construction Management (allowance)

$100,200

$100,200

Total

$617,384

$619,831

 

MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE

 

This action does not affect the Alameda Municipal Code.

 

ENVIRONMENTAL REVIEW

 

The existing California Environmental Quality Act (CEQA) Mitigated Negative Declaration (MND) from the previous 2014 lagoon dredging project was used for this project. The US Army Corps of Engineers Nationwide Permit and California Regional Water Quality Control Board 401 Water Quality Certification have already been issued for this project. No additional environmental review is required under CEQA to accept the completed improvements.

 

CLIMATE IMPACTS

 

Dredging work was performed during the annual draining of the lagoons to minimize contact of excavated sediment with the lagoon waters and natural habitat. Work occurred during the dry season, which also minimized storm water runoff entering into the lagoons. The dredging project overall helps restore the original capacity of the lagoon system for better storage and treatment of rainfall runoff and future increased runoff due to climate change.

 

RECOMMENDATION

 

Accept the work of Innovative Construction Solutions for the Alameda South Shore lagoons 3 and 5 dredging project, No. P.W. 09-19-49.

 

CITY MANAGER RECOMMENDATION

 

The City Manager concurs with the recommendation to accept the work of innovative construction solutions for the Alameda South Shore lagoons 3 and 5 dredging project.

 

Respectfully submitted,

Erin Smith, Public Works Director

 

By,

Andrew Nowacki, Associate Engineer

 

Financial Impact section reviewed,

Annie To, Finance Director

 

cc:                     Eric Levitt, City Manager