File #: 2021-676   
Type: Consent Calendar Item
Body: City Council
On agenda: 3/16/2021
Title: Recommendation to Authorize the City Manager to Accept the Improvements Completed by Alameda Point Partners, for Tract 8336, Site A, Phase 1, at Alameda Point. (Public Works 310)

Title

 

Recommendation to Authorize the City Manager to Accept the Improvements Completed by Alameda Point Partners, for Tract 8336, Site A, Phase 1, at Alameda Point. (Public Works 310)

 

Body

 

To: Honorable Mayor and Members of the City Council

 

EXECUTIVE SUMMARY

 

Tract 8336 subdivided 21.35 acres of land located at Site A, Phase 1, Alameda Point creating twelve parcels and remainder parcels. Alameda Point Partners completed a portion of the improvements, as detailed in the table below and staff is recommending that the City Council accept them as completed and reduce the amount of the surety.

 

BACKGROUND

 

On July 20, 2016, the City Council approved Tentative Map Tract 8336 per City of Alameda (City) Resolution No. 15187.  On March 7, 2017, the City Council established Community Facilities District No.17-1 (Alameda Point Public Services District) to levy special taxes and fees for City-provided municipal services to Site A.  On March 21, 2017, the City Council adopted Resolution No. 15244 approving the first final map and bond for Site A, Phase 1, authorizing the execution of a Public Improvement Agreement (PIA) with Alameda Point Partners, and rejecting the offers of dedications and easements for Tract 8336.  The offers of dedication remain open until accepted by the City Council.

 

DISCUSSION

 

The public improvements for Tract 8336 at Site A, Phase 1 at Alameda Point development are comprised of 9 infrastructure sub-phases in accordance with Exhibit C of the PIA for the project dated March 21, 2017. 

 

Staff recommends the acceptance of the following completed public improvements:

 

Sub-Phase

Description

Completion

1

Building Demolition, Remediation, Utility Abandonment, Site Leveling

Yes

2

W. Tower Avenue/  W. Atlantic Avenue Improvements

Yes

3

Storm Drainage Outfall

Yes

4

Wastewater Pump Station

Yes

5

Off-Site Wastewater Trunk Main

Yes

6

Secondary Streets and Utilities

Yes, As-Noted Below

7

Bulkhead Stabilization, Levee, and Ground Improvement

Yes

8

Waterfront Park

No

9

Neighborhood Park

Yes

 

The following exceptions apply to Sub-Phases 6 and 8. All other sub-phases are otherwise complete:

 

Sub-Phase 6, Secondary Streets and Utilities:

                     All streetlights adjacent to Blocks 6, 7, 8, and 9 are not recommended for acceptance due to ongoing block construction that has damaged multiple streetlights.

                     Sidewalk and frontage improvements adjacent to Block 9 on Orion Street, Coronado Avenue, and Ardent Way frontages are not complete.

 

Sub-Phase 8, Waterfront Park:

                     The park is not complete and is not part of this recommendation for acceptance of improvements.

 

Alameda Point Partners provided surety for the public improvements for Tract 8336 with a Performance Bond and Labor and Materials Bond each in the amount of $42,900,844.00.  Following the acceptance of the completed improvements listed above, the Performance Bond and Labor and Materials Bond will each be reduced to $5,546,296.00 as a surety of the remaining work.  Per the PIA, Alameda Point Partners will provide a warranty bond in the amount of 10% of the work completed.

 

Construction of the public improvements for Tract 8336, with the exceptions of the items noted above for Sub-Phases 6 and 8, are in pursuant to the PIA and its terms and conditions has been completed by Alameda Point Partners.  The completed work is acceptable to the Public Works Department.

 

ALTERNATIVES

 

                     Accept the improvements completed by Alameda Point Partners for Tract 8336 at Site A, Phase 1, at Alameda Point, as recommended.

                     Remand the project back to staff for further consideration and evaluation of the completed improvements.

 

FINANCIAL IMPACT

 

All listed tract improvements were constructed by Alameda Point Partners.  Parcels within the tract are or will be assessed ad valorem property taxes and other City-wide property related fees.  Per the City’s Policy of Fiscal Neutrality, costs of City municipal services in excess of those covered by ad valorem property taxes and City-wide property related fees will be paid for by taxes levied from Community Facilities District No.17-1 (Alameda Point Public Services District).

 

MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE

 

This action does not affect the Alameda Municipal Code.

 

ENVIRONMENTAL REVIEW

 

Per City Resolution No. 14891, the City Council certified the Final Alameda Point Environmental Impact Report (FEIR) (State Clearinghouse No. 201312043) under the California Environmental Quality Act (CEQA), California Public Resources Code Section 21000 et seq. and adopted written findings and a Mitigation Monitoring and Reporting Program (MMRP) on February 4, 2014, for the Alameda Point Project, including the Town Center Plan area which contains Site A.

 

RECOMMENDATION

 

Authorize the City Manager to accept the improvements completed by Alameda Point Partners, for Tract 8336 Site A, Phase 1, at Alameda Point.

 

CITY MANAGER RECOMMENDATION

 

The City Manager requests authorization to accept the improvements completed by Alameda Point Partners for Tract 8336 Site A, Phase 1.

 

Respectfully submitted,

Erin Smith, Public Works Director

 

By,

Russ Thompson, Interim City Engineer

Sarah Lee, Senior Engineer

 

Financial Impact section reviewed,

Annie To, Finance Director

 

cc:                     Eric Levitt, City Manager