File #: 2021-1331   
Type: Consent Calendar Item
Body: City Council
On agenda: 10/19/2021
Title: Recommendation to Accept the Work of NEMA Construction for the Shoreline Park Pathway Lighting Project, No. P.W. 10-20-38. (Public Works 60341591)
Title

Recommendation to Accept the Work of NEMA Construction for the Shoreline Park Pathway Lighting Project, No. P.W. 10-20-38. (Public Works 60341591)

Body

To: Honorable Mayor and Members of the City Council

EXECUTIVE SUMMARY

On February 16, 2021, the City Council awarded a contract to NEMA Construction in the amount of $653,400, which included a 10% contingency, for the removal and replacement of approximately one-half mile of exterior pathway lighting infrastructure. The project included the removal and replacement of approximately one-half mile of exterior pathway lighting infrastructure. The improvements executed under the subject contract are complete and acceptable to staff. Staff is now recommending that the City Council accept the work.

BACKGROUND

Shoreline Park consists of approximately one-half mile of pathways with approximately three acres of park space that is enjoyed year-round by residents. One of the park amenities is the pathway lighting system that supports continuous use of the park. The pathway lighting system is a key safety feature of the park but was in disrepair and had many failing components.

The work included the installation of new lighting control cabinets, conduit, conductors, pull boxes and 68 new light fixtures, while ensuring the operations of the existing public restrooms, SCADA and sluice gates' electrical supply during the construction phases.

Phase 1, Areas 1-7 included full replacement of approximately 22 bollards and 22 Cleveland Light Posts including new concrete foundations, pull boxes, conduits and exterior direct burial conductors.

Phase 2, Areas 8-11 included demolition of existing foundations and installation of approximately 23 bollards and one Cleveland Light Post while re-using existing pull boxes, conduit and conductors

DISCUSSION

On February 16, 2021, the City Council awarded a contract in the amount of $653,400, including contingencies, to NEMA Construction. The project was completed in accor...