File #: 2023-2800   
Type: Consent Calendar Item
Body: City Council
On agenda: 3/7/2023
Title: Recommendation to Accept the Work of Ranger Pipelines, Inc. for Cyclic Sewer Replacement Project, Phase 18, No. PW 09-21-34. In accordance with the California Environmental Quality Act (CEQA), this project is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction). (Public Works 31041520)

Title

 

Recommendation to Accept the Work of Ranger Pipelines, Inc. for Cyclic Sewer Replacement Project, Phase 18, No. PW 09-21-34. In accordance with the California Environmental Quality Act (CEQA), this project is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction). (Public Works 31041520)

 

Body

 

To: Honorable Mayor and Members of the City Council

 

From: Jennifer Ott, City Manager

 

EXECUTIVE SUMMARY

 

On October 15, 2019, the City Council awarded a five-year agreement with Ranger Pipelines, Inc. in an amount not-to-exceed a total five-year expenditure of $28,924,389.83 for the Cyclic Sewer Replacement Project.  On November 8, 2021, the City of Alameda (City) issued a Notice to Proceed for the third year of the agreement in an amount not-to-exceed $5,779,826.75, including a 6.15% contingency, for Phase 18. The project replaced approximately 2.9 miles of sewer main, associated manholes, and lower laterals.  The improvements executed under the subject contract are complete and acceptable to staff.  Staff is now recommending that the City Council accept the work.

 

BACKGROUND

 

The work in this contract served as Project Year 7 of the 20-Year Rehabilitation Program included in the City’s 2015 Sewer Master Plan. The Sewer Master Plan utilized information collected through maintenance, inspection, and monitoring activities to assess system condition and capacity.  The results were used to identify and prioritize sewer system capital improvement needs in a 20-Year Rehabilitation Program structured to be consistent with the City’s sewer rate structure, and to maintain compliance with the 2014 Consent Decree between the City and the U.S. Environmental Protection Agency (N.D. Cal., Consolidated Case Nos. C09-00186-RS and C09-05684-RS). Project Year 7 replaced approximately 2.9 miles of existing old and deteriorating sanitary sewer main.  Completion of this work is required for compliance with the 2014 Consent Decree which requires the City to rehabilitate no less than 2.6 miles of sewer main and associated lower laterals and manholes per year, based on a cumulative total. As reported in the City’s Consent Decree Annual Report dated June 30, 2022, the City has replaced 27.7 miles of sewer main since the effective date of the consent decree in 2014.  This exceeds the 23.4 miles required. This work is also consistent with, and furthers, the objectives of the City’s 2017 Sewer System Management Plan and adopted Capital Improvement Program.

 

DISCUSSION

 

On October 15, 2019, the City Council awarded a five-year agreement with Ranger Pipelines, Inc. in an amount not-to-exceed a total five-year expenditure of $28,924,389.83 for the Cyclic Sewer Replacement Project.  On November 8, 2021, the City issued a Notice to Proceed for the third year of the agreement in an amount not-to-exceed $5,779,826.75, including a 6.15% contingency, for Phase 18.

 

The project was completed in accordance with the plans and specification and is acceptable to the Public Works Department.  The final cost, including all extra work orders, is $5,779,796.

 

ALTERNATIVES

 

                     Accept the work as presented.

                     Do not accept the work and give staff alternate direction.

 

FINANCIAL IMPACT

 

The project was budgeted in the Capital Improvement Program (Project No. C21000) with funding from the Sewer Capital Improvements Enterprise Fund (Fund 501). No additional appropriations are needed. There is no impact to the General Fund.

 

MUNICIPAL CODE/POLICY DOCUMENT CROSS REFERENCE

 

This action is consistent with the Alameda Municipal Code.

 

ENVIRONMENTAL REVIEW

 

In accordance with the California Environmental Quality Act (CEQA), this project is categorically exempt from further environmental review pursuant to CEQA Guidelines Sections 15301 (Existing Facilities) and 15302 (Replacement or Reconstruction).

 

CLIMATE IMPACTS

 

This project rehabilitated the sanitary sewer collection system and reduced the amount of infiltration and inflow from stormwater and groundwater. This helps prevent overflow of the sewer system and creates infrastructure more resilient to the effects of climate change.

 

RECOMMENDATION

 

Accept the Work of Ranger Pipelines, Inc. for Cyclic Sewer Replacement Project, Phase 18, No. PW 09-21-34.

 

 

Respectfully submitted,

Erin Smith, Public Works Director

 

By,

Shilpa Patel, Assistant Engineer

 

Financial Impact section reviewed,

Margaret O’Brien Finance Director