File #: 2023-3008   
Type: Consent Calendar Item
Body: City Council
On agenda: 5/16/2023
Title: Recommendation to Authorize the City Manager to Execute a Fourth Amendment to the Agreement with CDM Smith to Increase Compensation by $420,000, Including Contingencies, for a Total Aggregate Compensation Not-to-Exceed $3,578,930, to Complete the Plans and to Provide Construction Support for the Central Avenue Safety Improvement Project. In accordance with the California Environmental Quality Act (CEQA), this Project is Categorically Exempt Under CEQA Guidelines Section 15301(c) Existing Facilities (Minor Alterations to Existing Facilities Including Bicycle Facilities) and Section 15304(h) (Minor Alterations to Land and the Creation of Bicycle Lanes on Existing Public Rights of Way). (Planning, Building and Transportation 20962740)
Attachments: 1. Exhibit 1 - Agreement, 2. Exhibit 2 - First Amendment, 3. Exhibit 3 - Second Amendment, 4. Exhibit 4 - Third Amendment, 5. Exhibit 5 - Fourth Amendment
Title

Recommendation to Authorize the City Manager to Execute a Fourth Amendment to the Agreement with CDM Smith to Increase Compensation by $420,000, Including Contingencies, for a Total Aggregate Compensation Not-to-Exceed $3,578,930, to Complete the Plans and to Provide Construction Support for the Central Avenue Safety Improvement Project.
In accordance with the California Environmental Quality Act (CEQA), this Project is Categorically Exempt Under CEQA Guidelines Section 15301(c) Existing Facilities (Minor Alterations to Existing Facilities Including Bicycle Facilities) and Section 15304(h) (Minor Alterations to Land and the Creation of Bicycle Lanes on Existing Public Rights of Way). (Planning, Building and Transportation 20962740)
Body

To: Honorable Mayor and Members of the City Council

From: Jennifer Ott, City Manager

EXECUTIVE SUMMARY

Staff is requesting that the City Council authorize the City Manager to execute a Fourth Amendment of the CDM Smith contract to allow for continued Caltrans coordination, the completion of design work for the third roundabout and additional construction support on the Central Avenue Safety Improvement Project (Central Avenue Project). The Fourth Amendment increases compensation by $420,000, including contingencies, for a total aggregate compensation not-to-exceed $3,578,930.

BACKGROUND

Project Objectives: The Central Avenue Project implements the City of Alameda's (City) 2018 Transportation Choices Plan, 2019 Climate Action and Resiliency Plan, 2019 Intersection Daylighting Policy, 2019 Lane Widths Policy, 2021 Vision Zero Action Plan and 2022 Active Transportation Plan by achieving four overarching objectives:
1. Reduce crashes and improve safety for all modes of travel and for all members of the community including school children, seniors, people with disabilities, bicyclists, transit riders and automobile drivers;
2. Improve bicycle and pedestrian access and safety between West Alameda and Central Alameda and...

Click here for full text